|
PMP Sample Questions
- A project manager performs Earned Value Analysis and finds the following results:
AC: 220,000, PV: 250,000, EV: 220,000.
- CV = 0.
- CV = 30,000.
- CV = -30,000.
- CV = 1
Answer: A
- During a company event, you had the opportunity to talk to a colleague project manager. He told you that in his current project actual costs are 15% under cumulated costs scheduled for today.
What do you think?
- The information available is not sufficient to assess project performance.
- The project will probably be completed with total costs remaining under budget.
- A significant cost increase during the further course of the project will probably bring the costs back to baseline level.
- Original cost planning must have been poor to allow this variance.
Answer: A
- Which is true regarding projects?
- A project is a unique service undertaken to create a temporary product.
- A project is a unique endeavor undertaken to create a temporary service.
- A project is a temporary endeavor undertaken to create a unique product or service.
- A project is a temporary product undertaken to create a unique endeavor or service
Answer: C
- Which of the following statements describes the relationship between project phases and the project life cycle?
- The project lifecycle contains the iterative incremental elements inside a project phase.
- Collectively, the project phases are known as the project life cycle.
- The project lifecycle is regarded as a sequence of project activities while phases are defined to control the overlapping of activities.
- The project lifecycle contains the repetitive elements inside a project phase
Answer: B
- A project management team discusses what scope means in a project.
All of the following statements are true except
- The processes, tools, and techniques used by project scope management are mostly depending on the application area.
- Product scope includes features and functions that are to be included in a product or service.
- Project scope includes the work that must be done in order to deliver a product with the specified features and functions.
- Project Scope Management includes the processes required to ensure that the project includes all the work required and only the work required.
Answer: A
- What is the S-curve in project management?

- A graph that is generated if a normal curve is integrated.
- A graph that is to be integrated to generate a normal curve.
- A metaphoric description of the short term uncertainties that are present in every project.
- The graph that describes the typical growth of earned value during the course of the project.
Answer: D
- The output of the resource planning process is a document "resource requirements". This a description of what types of resources are required in what quantities...
- where the term resources is limited to equipment and materials.
- for each element at the lowest level of the work breakdown structure.
- where the term resources is limited to human resources.
- to be obtained solely from the performing organization.
Answer: B
- The major output document of Scope definition is the.
- Hierarchically structured WBS.
- Flat Activity List.
- Narrative Scope Statement.
- The Project Charter for the project manager
Answer: A
- In regards of a cost baseline all of the following is true except
- It is a time-phased budget that will be used to measure and monitor cost performance on the project.
- It can be easily created and updated as necessary.
- It is developed by summing estimated costs by period.
- It is usually displayed in the form of an S-curve.
Answer: B
- Which is not true in regard of RoI (Return on Investment)?
- It defines the cumulated net income from an investment at a given point in time or during a defined period.
- It includes investment, direct and indirect costs and may include allowances for capital cost, depreciation, risk of loss, and/or inflation.
- It is generally stated in currency units, as a percentage or as an index figure.
- It is the time when cumulated net income is equal to the investment.
Answer: D
« Previous || Next »
PMP Sample Question Number :
1-10|
11-20|
21-30|
31-40|
41-50|
51-60|
61-70|
71-80|
81-90|
91-100|
101-110|
111-120|
121-130|
131-140|
141-150|
151-160
|
|